Pendientes de Campo

Open items a resolver antes/durante reinstalación — 20 registros.

# ITEM ID CATEGORY DESCRIPTION AFFECTED CIRCUITS IMPACT IF NOT RESOLVED REQUIRED ACTION RESPONSIBLE TARGET PHASE PRIORITY STATUS
1 OI-001 MCC ENGINEERING MCC does not exist. No breaker schedule, no bus rating, no utility service data for Houston facility. SU-001, SU-002, DC-PWR-01/02/03, AC-PWR-PX, SU-010 ENTIRE LINE CANNOT BE ENERGIZED. All 1,335HP blocked. Engage licensed PE. Define Houston utility service kVA. Design MCC with full breaker schedule. Verify protection coordination for all circuits. PE / Electrical Eng. PRE-INSTALL P1 OPEN
2 OI-002 BREAKER SIZING CB-001 (ABB D30) confirmed at only 30A. Grossly undersized for 1,335HP system. May be isolation breaker only. SU-002 Panel P-01 main feed unprotected or underprotected. Verify CB-001 function (isolation vs protection). Size proper main breaker for P-01 feed from MCC. PE / Electrical Eng. PRE-INSTALL P1 OPEN
3 OI-003 DECOILER MOTOR Motor HP/V/FLA/Frame completely unknown. Nameplate not readable in any photo. DC-PWR-03, DECO-MTR, PWR-DECO Cannot size cable, breaker, or verify PF20P #3 drive configuration. Decoiler circuit 100% blocked. Photograph decoiler motor nameplate at Houston receiving. Record HP, V, FLA, Frame, RPM, S/N. Field Tech RECEIVING P1 OPEN
4 OI-004 HPU MOTORS HPU Motor #1 (M-10) and #2 (M-11) nameplates unreadable. No circuit info. PWR-HPU1, PWR-HPU2 HPU circuits cannot be wired. HPU may auto-start — safety risk. Photograph both HPU motor nameplates. Trace circuits back to panel/starter. LOTO before any work. Field Tech RECEIVING P1 OPEN
5 OI-005 12 UNASSIGNED MOTORS 12 motors confirmed by nameplate but NO panel/drive/starter/cable/route documented: Marathon 100HP, 60HP, 4HP; WEG 125HP, 10HP; TECO 10HP ×2; Baldor 1.5HP; Decoiler; HPU ×2; Roll motors nameplate FLA. PWR-MARA100, PWR-MARA60, PWR-WEG125, PWR-TECO10A/B, PWR-WEG10, PWR-BALDOR15, PWR-MARA4, PWR-HPU1/2, PWR-DECO, PWR-ROLL-ALL 12 motor circuits cannot be reconnected. ~500+ HP of unassigned load. Resolve via schematic #13951 OR trace each motor back to panel/drive/starter at Houston. Field Tech + Eng. INSTALL P1 OPEN
6 OI-006 CUT CABLE GROUPS 8 disconnected cable groups (DISC-01 to DISC-08) with unknown destinations. Includes cut ends, bare copper, contaminated JBs, possible thermal damage. DISC-01 to DISC-08 8 circuit groups potentially safety-critical. Short circuit risk from bare copper (DISC-08). Possible carbonization (DISC-07). IMMEDIATE: Insulate all bare copper before transport. At Houston: tone-test EVERY conductor. Label and map. Replace damaged JBs and conduit. Field Tech RECEIVING + INSTALL P1 OPEN
7 OI-007 FIRMWARE MISMATCH PowerFlex 20P #1 runs FW V7.002, #2 runs FW V5.005. Different firmware on identical drives controlling parallel motors. SU-004, SU-005, DC-MTR-01, DC-MTR-02 Possible different control behavior between Drive #1 and #2. Commissioning risk. Contact Rockwell. Determine target firmware version. Update both drives to same FW before commissioning. Eng. / Rockwell Support PRE-COMMISSION P1 OPEN
8 OI-008 ETHERNET IP PLAN 6 of 9 networked devices have NO documented IP address. Only DL-205 (192.168.84.101) and PF525s (192.168.182.x) confirmed. ENET-01 to ENET-06 Network communication will fail. Cannot commission control system. Create Houston IP addressing plan for ALL EtherNet/IP devices. Document Hirschmann port assignments. Controls Eng. PRE-COMMISSION P1 OPEN
9 OI-009 HIRSCHMANN PORT MAP Hirschmann SPIDER STX port-to-device mapping not documented. 7+ devices connected but no port assignment table. ENET-01 to ENET-09 Cannot verify network topology or troubleshoot communication issues. Document physical port assignment at Hirschmann switch. Create network topology diagram. Controls Eng. PRE-COMMISSION P1 OPEN
10 OI-010 P-01 WIRE DESTINATIONS Terminal block wire numbers confirmed by audit (01xxx, 5xx/7xx, ICO, Bxxxx series) but field destinations NOT closed. PLC-006, PLC-007, PLC-008, PLC-009 PLC I/O field wiring cannot be landed without tone-test. Interlocks (ICO) safety-critical. Obtain schematic #13951 OR tone-test all outgoing conductors from P-01. Priority: ICO series first (safety). Field Tech + Eng. INSTALL P1 OPEN
11 OI-011 AC890 I/O BUNDLE P-01 to P-03 I/O multiconductor bundle mapped at bundle level only. Individual conductor-to-terminal mapping missing. PLC-001 Cannot reconnect PLC control signals to VFD I/O boards (X10-X15). Tone-test each conductor in bundle. Map to specific AC890 I/O board terminals and pins. Field Tech INSTALL P2 OPEN
12 OI-012 TRANSFORMER TAP SETTING Control transformer ACME supplies 110VAC (Rexroth) and 120VAC (Parker). Houston voltage may differ from Tulsa area. SU-003, SOL-001 to SOL-005 Solenoid valves may malfunction or burn if tap setting wrong. Parker REQUIRES 120V (not 110V). Verify transformer primary/secondary tap configuration for Houston voltage. Confirm separate taps for 110V and 120V circuits. Electrical Eng. PRE-COMMISSION P1 OPEN
13 OI-013 CONTINENTAL SOLENOID HV-CONT-01 Continental EBA 1CN4-AC — solenoid voltage completely unknown. SOL-006 Cannot wire solenoid without knowing required voltage. Identify valve physically. Measure coil resistance. Confirm supply voltage. Field Tech INSTALL P2 OPEN
14 OI-014 AC890 DC BUS ARCHITECTURE Parker AC890 rack DC bus architecture (shared vs individual per drive) NOT confirmed. SU-010, AC890-PWR-RACK Cannot properly size input breaker/cable or verify protection coordination for 325HP rack. Obtain Parker documentation for AC890 rack. Confirm DC bus sharing mode. Eng. / Parker Support PRE-INSTALL P1 OPEN
15 OI-015 BLOWER MOTOR SOURCING Blower motors P/N 303-063 (1HP each, on MTR-01 and MTR-02) — exact panel source (P-01 vs P-04) not confirmed. DC-BLWR-01, DC-BLWR-02 DPFV blowers MUST run before main motors. If source unknown, cannot verify branch protection. Trace blower power cables to source panel. Confirm branch breaker rating. Field Tech INSTALL P2 OPEN
16 OI-016 LIMIT SWITCH CIRCUITS 4+ Allen-Bradley 802T-AP limit switches confirmed on machine but circuit connections NOT documented. FD-012 Interlock/position detection circuits cannot be reconnected. Map each limit switch to PLC DI input. Document tag, function, and wire route. Field Tech INSTALL P2 OPEN
17 OI-017 THERMOCOUPLE DESTINATION MTR-01 thermocouple P1/P2 (N.C./N.O.) — destination terminal (PLC input or drive input?) not documented. PLC-005, DC-THERMO-01 Motor temperature monitoring circuit cannot be completed. Verify thermocouple destination: PLC DI or drive analog input. Confirm N.C./N.O. configuration. Eng. INSTALL P2 OPEN
18 OI-018 ROLL MOTOR NAMEPLATES 6 roll motor nameplates NOT photographed. HP values come from drive tags only (75/100/75/25/25/25). FLA not confirmed. ROLL-01 to ROLL-06, PWR-ROLL-ALL Cable sizes are ESTIMATES only. Cannot verify overload settings or drive configuration. Photograph all 6 roll motor nameplates at Houston. Record HP, V, FLA, RPM, S/N. Field Tech RECEIVING P1 OPEN
19 OI-019 SCHEMATIC #13951 Braner/Delta schematic drawing #13951 referenced but not available. Would resolve majority of unknown wire destinations. ALL unresolved circuits Without this schematic, every unknown destination requires physical tone-test. Contact Braner/Delta for schematic package #13951. If unavailable, plan full tone-test campaign at Houston. Eng. / Procurement PRE-INSTALL P1 OPEN
20 OI-020 FIREWIRE CABLE INSPECTION 6 IEEE 1394a FireWire cables are IRREPLACEABLE (discontinued standard). No spares available. FW-001 to FW-006 If any FireWire cable is damaged, Parker AC890 sync network fails. All 6 roll drives inoperative. Inspect ALL 6 FireWire connectors immediately at Houston receiving. Photograph connector condition. Handle with extreme care during transport. Field Tech RECEIVING P1 OPEN