Procedimiento de Comisionado

Secuencia de re-energización y arranque (55 pasos) — 55 registros.

STEP PHASE TASK CIRCUIT IDs DETAIL VERIFICATION HOLD POINT RESPONSIBLE
1 1-RECEIVING Inspect ALL equipment for shipping damage ALL Visual inspection of panels P-01, P-03, P-04, P-05, AC890PX, DL-205. Check for bent enclosures, loose components, broken connectors. Document damage with photos. Compare to deinstallation photos. YES Field Tech
2 1-RECEIVING Inspect FireWire cables (IRREPLACEABLE) FW-001 to FW-006 Locate all 6 IEEE 1394a FireWire segments in P-03 AC890 rack. Check each 6-pin connector for bent pins, cracked housing, damaged shielding. Photograph each connector. Log condition. If any cable damaged, STOP and contact Parker. YES Field Tech
3 1-RECEIVING Photograph all unreadable motor nameplates PWR-DECO, PWR-HPU1, PWR-HPU2, ROLL-01-06 Decoiler motor, HPU M-10 and M-11, all 6 roll motors. Record: HP, V, FLA, RPM, S/N, Frame. Update Master Cable Schedule with confirmed data. YES Field Tech
4 1-RECEIVING Insulate all bare copper immediately DISC-08, DISC-04 DISC-08 has bare copper hanging from aux panel — short circuit risk during handling. DISC-04 has bare wire ends. Heat shrink or tape all exposed conductors. Photograph before and after. NO Field Tech
5 1-RECEIVING Assess DISC-03 contaminated junction box DISC-03 Floor-level JB severely contaminated. UL sticker degraded. Evaluate: clean and reuse vs replace entire NEMA 12 box. Order replacement if needed. NO Field Tech
6 2-GROUND Install main ground bus and building ground FD-007, all GND circuits Establish Houston facility ground system. Connect main ground bus. Verify ground resistance <5 ohm with ground resistance tester. YES Electrical Eng.
7 2-GROUND Bond all panel frames to ground bus P-01, P-03, P-04, P-05, AC890PX, DL-205 #6 AWG green/yellow from each panel frame to ground bus through JBOX-05 distribution. Verify continuity from each panel frame to main ground. <1 ohm bonding resistance. YES Field Tech
8 2-GROUND Bond motor frames to ground system FD-003, FD-004, all motor GND Connect ground conductor to MTR-01, MTR-02, MTR-300, and all motor frames. Verify bonding continuity motor frame to ground bus. YES Field Tech
9 3-MOUNT Position and anchor P-01 (Main Panel) N/A Mount P-01 at machine centerline. Level. Anchor to floor/structure. Verify all internal components secure from shipping. Visual inspection. Door operation. DIN rail components seated. NO Mechanical + Electrical
10 3-MOUNT Position and anchor P-03 (AC890 VFD Rack) N/A Mount P-03 adjacent to P-01. Ensure adequate ventilation clearance per Parker specs. Visual. Ventilation clearance measured. NO Mechanical + Electrical
11 3-MOUNT Position and anchor P-04 (DC Drive Cabinet) N/A Mount P-04 adjacent to P-01. Verify Shawmut fuses present and intact. Visual. Fuse check. NO Mechanical + Electrical
12 3-MOUNT Position P-05 (Operator Console) N/A Mount at operator station. Verify PanelView screen intact. Visual. NO Mechanical
13 3-MOUNT Position AC890PX (Flattener drive) N/A Mount standalone cabinet near P-03. Ventilation clearance per Parker specs. Visual. NO Mechanical
14 3-MOUNT Position DL-205 Cabinet N/A Mount separate cabinet. Verify DirectLOGIC 205 rack intact. Visual. NO Mechanical
15 4-CONDUIT Install cable tray MCC → P-01 → P-03/P-04 SU-002, DC-PWR-01/02/03, SU-010, AC-PWR-PX Main power cable tray from MCC location to panel lineup. Route verified against deinstallation photos. Supports rated for cable weight. NO Electrical
16 4-CONDUIT Install conduit P-04 → pit → JBOX-01 → JBOX-02 → motors DC-MTR-01/02, DC-FLD-01/02, DC-ENC-01/02 Subterranean conduit route for DC motor power and signal cables. ~15m per route section. Conduit continuity. Pull string installed. Verify pit access. NO Electrical
17 4-CONDUIT Install safety conduit P-01 → P-03 STO-002, AC890-STO Dedicated conduit for STO safety wiring. MUST be separate from power conduit. Separation verified from power cables per NEC. NO Electrical
18 4-CONDUIT Install field conduit P-01 → JBOXes 01-08 JBF-001, JBF-002, JBF-003, FD-005-010 Conduit runs to all 8 field junction boxes. Routes match deinstallation documentation. NO Electrical
19 4-CONDUIT Replace damaged conduit sections DISC-01, DISC-04 DISC-01 conduit disconnected at base leveler. DISC-04 flexible conduit disconnected. New conduit installed. Connectors secured. NO Electrical
20 5-POWER-AC Pull MCC → P-01 main feed cables SU-002 L1/L2/L3 + GND. Cable size per MCC engineering (3/0 AWG+ XHHW-2). Megger test >1 MΩ at 1000V. Phase identification labeled. YES Electrical
21 5-POWER-AC Pull MCC → P-04 drive feed cables (PF20P #1 and #2) DC-PWR-01, DC-PWR-02 2/0 AWG XHHW-2 per circuit. L1/L2/L3 + GND per drive. Megger test. Phase ID. Cable label at both ends. YES Electrical
22 5-POWER-AC Pull MCC → P-04 decoiler drive feed DC-PWR-03 Cable size PENDING motor nameplate confirmation (OI-003). HOLD — Cannot execute until OI-003 resolved. YES Electrical
23 5-POWER-AC Pull MCC → P-03 AC890 rack feed SU-010, AC890-PWR-RACK Through TCI reactors KDRH3L/KDRF2L. 250A+ estimated. Megger test. Reactor connections verified. YES Electrical
24 5-POWER-AC Pull MCC → AC890PX flattener feed AC-PWR-PX ~250 MCM estimated. Size PENDING Parker documentation (OI-014). Megger test. YES Electrical
25 5-POWER-AC Land 480VAC at P-01 main breaker CB-001 SU-002 L1/L2/L3 at CB-001 line side 1-3-5. Verify CB-001 function (OI-002). Torque to manufacturer spec. Verify phase rotation with meter. YES Electrical
26 6-POWER-DC Pull armature cables P-04 → JBOX-01 → JBOX-02 → MTR-01 DC-MTR-01 (cable E315270) 4/0 AWG XHHW-2. Route through pit subterranean. Megger test. Cable label E315270 verified. Polarity marked A+/A-. YES Electrical
27 6-POWER-DC Pull armature cables P-04 → JBOX-01 → JBOX-02 → MTR-02 DC-MTR-02 4/0 AWG XHHW-2. Same route as MTR-01. Megger test. Polarity marked. YES Electrical
28 6-POWER-DC Pull field cables to MTR-01 and MTR-02 DC-FLD-01, DC-FLD-02 #10 AWG shielded. Bundled with armature conduit. Measure field resistance before connecting: MTR-01 = 11.3 ohm, MTR-02 = same. YES Electrical
29 6-POWER-DC Land armature cables at JBOX-02 TB70-72 FD-002 TB-70, TB-71, TB-72 terminal blocks. Power/control separation point. Verify TB labeling matches deinstallation photos. Torque to spec. YES Electrical
30 6-POWER-DC Land armature A1/A2 at MTR-01 and MTR-02 FD-003, FD-004 A1=+, A2=−. DO NOT INVERT — reverse causes reverse rotation + possible runaway. Polarity verified with voltmeter (brief bump test at low voltage if possible). YES Electrical
31 6-POWER-DC Pull flattener motor cables AC890PX → MTR-300 AC-MTR-300 350 MCM per phase. U/V/W at drive, T1/T2/T3 at motor. Megger test. Phase sequence verified. YES Electrical
32 7-SAFETY Wire E-stop circuit P-05 → P-01 Banner relay STO-001 #16 AWG 2C safety grade. S31/S32/S34 inputs at Banner ES-UA-5A. Continuity test. Dual-channel function verified. YES Electrical
33 7-SAFETY Wire STO circuits P-01 → P-03 (6 AC890 drives) STO-002 6 separate runs #16 AWG shielded. X11 STO A/STO B at each AC890. Test each: press E-stop → drive must NOT enable. Release → drive enables. YES Electrical
34 7-SAFETY Wire STO circuit P-01 → AC890PX STO-003 #16 AWG shielded to AC890PX X11 STO A/STO B. Same test as Step 33 for flattener drive. YES Electrical
35 8-CONTROL Verify 24VDC power supplies in P-01 24V-001, 24V-002, 24V-003 Phoenix QUINT 30A (primary), PULS ML30 (secondary), SOLA SDN (tertiary). Verify all present and undamaged. Measure output voltage on each PSU before connecting bus. NO Electrical
36 8-CONTROL Wire 24VDC distribution to field JBOXes 24V-004, JBF-002 24V/0V/ENA signals to JBOX-04 and JB-FIELD-02. Verify 24VDC present at each JB. Measure voltage. NO Electrical
37 8-CONTROL Wire JB-FIELD-01 (confirmed wire labels) JBF-001 Wire labels: 2561,2561A,1025,702,3161,3121,3081,M25,4025. Panel-side destinations require tone-test (OI-010). Tone-test each wire. Map to panel terminal. Document. YES Field Tech
38 8-CONTROL Wire JB102 motor control (FWD/REV/COM) JBF-003 Terminals 1-9: FWD(1), REV(2), COM(3), MOTOR(4-9). Check for corrosion. Inspect terminals. Replace if corroded. Verify continuity. NO Electrical
39 8-CONTROL Wire solenoid valve circuits (110/120VAC) SOL-001 to SOL-005 #16 AWG 2C+GND from transformer secondary. Rexroth E33 @110V, Parker @120V. Verify transformer tap matches required voltage (OI-012). Test each solenoid energizes. NO Electrical
40 8-CONTROL Wire encoder cables to drives PLC-002, PLC-003, PLC-004 FSI encoder to L24ER HSC. UNICO transducers to PF20P #1/#2. Verify encoder signals with oscilloscope or drive diagnostic. NO Electrical
41 9-NETWORK Verify FireWire daisy chain in P-03 FW-001 to FW-006 Check all 6 segments. Node sequence: AC890PX(3)→Roll#1(1)→Roll#2(4)→Roll#3(5)→Roll#4(6)→Roll#5(7)→Roll#6(8). End terminator at Node 8. Visual inspection of each connection. Node 2 must remain empty. YES Controls Eng.
42 9-NETWORK Connect Ethernet cables at Hirschmann switch ENET-01 to ENET-09 Cat5e/6 STP RJ45 to each device. Requires IP plan (OI-008) and port map (OI-009). HOLD until IP plan complete. Then: ping each device from Hirschmann. YES Controls Eng.
43 9-NETWORK Verify DL-205 Ethernet connection ENET-07 Cable CB-0178/CB-1920. IP: 192.168.84.101. Ping 192.168.84.101 from Hirschmann network. NO Controls Eng.
44 10-DISC Tone-test and map DISC-01 (leveler area) DISC-01 Red/Green/Yellow/White cut ends at base leveler. Each wire identified, labeled, and mapped to destination. New conduit installed. YES Field Tech
45 10-DISC Tone-test and map DISC-06 (MCC floor area) DISC-06 Pink/Red AND Blue cut cables — mass on floor in front of MCC. Each conductor identified. May include interlock or safety wiring. YES Field Tech
46 10-DISC Process remaining DISC-02 to DISC-05, DISC-07, DISC-08 DISC-02-05, DISC-07-08 Tone-test, label, map, re-terminate each group. Replace thermally damaged cables (DISC-07). All conductors identified and reconnected or documented as spare. NO Field Tech
47 11-VERIFY Megger test ALL power cables ALL PWR-AC, PWR-DC circuits Insulation resistance >1 MΩ at 1000V DC for each power circuit. Log results per circuit. Fail = do not energize that circuit. YES Electrical Eng.
48 11-VERIFY Verify ALL ground bonds FD-007, all GND circuits Continuity test from every motor frame, panel frame, and equipment frame to main ground bus. <1 ohm bonding resistance for each connection. YES Electrical
49 11-VERIFY Verify phase rotation at P-01 SU-002 Phase rotation meter on L1/L2/L3 at P-01 main bus. Correct rotation confirmed (CW or as required by drives). YES Electrical
50 11-VERIFY Verify ALL safety circuits functional STO-001, STO-002, STO-003 Press E-stop → ALL drives must de-energize STO. Release → drives ready. Test with each drive individually AND all simultaneously. YES Safety Eng.
51 12-ENERGIZE Energize 24VDC control power only 24V-001, 24V-002, 24V-003 Turn on 24VDC PSUs. Verify voltage at all field distribution points. 24VDC ±2% at each JB and I/O module. YES Electrical Eng.
52 12-ENERGIZE Energize P-01 main 480VAC (CB-001) SU-002 Close MCC breaker feeding P-01. Verify 480V L-L at P-01 bus. Voltage measured. No smoke, arcing, or abnormal sounds. YES Electrical Eng.
53 12-ENERGIZE Energize P-04 drives one at a time DC-PWR-01, DC-PWR-02 Close dedicated breaker for PF20P #1 first. Verify drive powers up with no faults. Then PF20P #2. Drive display shows normal. No fault codes. Parameters verified. YES Electrical Eng.
54 12-ENERGIZE Energize P-03 AC890 rack SU-010, AC890-PWR-RACK Close rack input breaker. Verify all 6 drives power up. Check FireWire sync status. All drives show normal. FireWire communication confirmed. YES Electrical Eng.
55 12-ENERGIZE Energize AC890PX flattener drive AC-PWR-PX Close dedicated breaker. Verify drive powers up. Drive display normal. Base freq = 84Hz confirmed in parameters. YES Electrical Eng.